Fan balancing – Mission accomplished!

    bg-separatore
    Fan balancing – Mission accomplished!

    Once again on site for a critical balancing service following an urgent request on a UK paper production facility. Our technicians intervened quickly to analyze the problem and carry out the balancing of the fan impeller.

    The vibration measurements detected on the main air recirculation fan indicated a vibration of 30 mm / s @ 1X which was transmitted to the fan structure and to the other adjacent rotating machines.

    Following the inspection of the fan impeller, a balancing procedure was carried out which allowed the rotating machine to be restarted with vibrations below the alarm thresholds: 1.4 mm / s @ 1X.

    See also

    ISE is proud to be present “The Third Vibration Institute Middle East Training Conference”  24-26 October 2022. The 25th of October 2022 session 14-15.30 – Eng. […]

    ISE participated in the supply of a Twise® Site measurement and analysis system !! 36 channels for vibration, structural and electrical measurements to monitor the mechanical […]

    ISE is an OFFICIAL SPONSOR of MaintenanceStories, the reference event for Italian Maintenance professionals. Registration for the HomeComing edition of MaintenanceStories 2022 is officially open: join […]

    GDPR Cookie Consent with Real Cookie Banner

      This site is protected by reCAPTCHA and the Google Privacy Policy and Terms of Service apply.


       I have read the privacy*

      * Required fields